Topics › Contract and consumer law
Contract and consumer law
Discharge of a contract
How contractual obligations come to an end: by performance (and its exceptions), by agreement, by frustration, and by actual or anticipatory breach.
- On the courses
- Pearson T Level, AQA A level, OCR A level, Eduqas A level, WJEC A level, Pearson BTEC
- Reading time
- About 15 minutes in the app
What this topic covers
- What discharge means
- Performance: the strict rule
- Performance: the exceptions
- Discharge by agreement
- Frustration: the doctrine
- Frustration: the leading cases
- Frustration: the limits
- The effect of frustration: the 1943 Act
- Discharge by breach
- Anticipatory breach
- Strengths and weaknesses
- Worked example
- Common mistakes and exam tips
Key cases
- Cutter v Powell (1795): A sailor who died before completing a voyage, and was to be paid only on completion, was owed nothing.
- Hoenig v Isaacs (1952): A decorator whose work had only minor defects had substantially performed, so was entitled to the price less the cost of repairs.
- Bolton v Mahadeva (1972): A central heating system that did not work properly and gave off fumes was not substantially performed, so nothing was payable.
- Sumpter v Hedges (1898): A builder who abandoned the work could not be paid for it, because the landowner had no real choice but to accept the half-built buildings.
- Taylor v Caldwell (1863): A contract to hire a music hall was frustrated when the hall burned down before the concerts.
- Krell v Henry (1903): Hiring a room to watch a coronation procession was frustrated when the procession was cancelled.
- Herne Bay Steam Boat Co v Hutton (1903): A boat hired to see the naval review and cruise round the fleet was not frustrated when the review was cancelled, because the fleet was still there.
- Davis Contractors Ltd v Fareham UDC (1956): A building contract was not frustrated just because labour shortages made it take much longer and cost much more.
- Hochster v De la Tour (1853): A courier told in advance that he would not be needed could sue at once, without waiting for the start date.
Key terms
- Discharge: When contractual obligations come to an end: by performance, agreement, frustration or breach.
- Substantial performance: Where a party has essentially completed their obligations with only minor defects, they are entitled to the price, less the cost…
- Frustration: When an event after the contract is made, which is neither party's fault, makes performance impossible, illegal or radically…
- Anticipatory breach: When a party makes clear, before performance is due, that they will not perform. The other party can treat the contract as ended…
- Repudiatory breach: A breach serious enough to let the innocent party end the contract, such as a breach of a condition or a serious breach of an…
- Condition: An important term that goes to the root of the contract. If it is broken, the innocent party can end the contract and claim…
- Warranty: A less important term. If it is broken, the innocent party can claim damages but cannot end the contract. (In everyday speech a…
Try a question
What can the innocent party do after a repudiatory breach?
- End the contract and claim damages, or affirm it and claim damages
- Only claim damages
- Nothing, because the contract continues
- Only end the contract, with no damages
Show the answer
End the contract and claim damages, or affirm it and claim damages. A repudiatory breach gives the innocent party a choice: terminate or affirm, and damages either way.
22 questions on this topic in the app, plus written questions marked by AI.
This page is a summary. The full topic in Veritas has the law step by step, worked examples, exam tips and practice questions. Full A4 revision sheets with the nutshell are part of Veritas Premium.