Discharge of a contract

How contractual obligations come to an end: by performance (and its exceptions), by agreement, by frustration, and by actual or anticipatory breach.

On the courses
Pearson T Level, AQA A level, OCR A level, Eduqas A level, WJEC A level, Pearson BTEC
Reading time
About 15 minutes in the app

What this topic covers

  • What discharge means
  • Performance: the strict rule
  • Performance: the exceptions
  • Discharge by agreement
  • Frustration: the doctrine
  • Frustration: the leading cases
  • Frustration: the limits
  • The effect of frustration: the 1943 Act
  • Discharge by breach
  • Anticipatory breach
  • Strengths and weaknesses
  • Worked example
  • Common mistakes and exam tips

Key cases

  • Cutter v Powell (1795): A sailor who died before completing a voyage, and was to be paid only on completion, was owed nothing.
  • Hoenig v Isaacs (1952): A decorator whose work had only minor defects had substantially performed, so was entitled to the price less the cost of repairs.
  • Bolton v Mahadeva (1972): A central heating system that did not work properly and gave off fumes was not substantially performed, so nothing was payable.
  • Sumpter v Hedges (1898): A builder who abandoned the work could not be paid for it, because the landowner had no real choice but to accept the half-built buildings.
  • Taylor v Caldwell (1863): A contract to hire a music hall was frustrated when the hall burned down before the concerts.
  • Krell v Henry (1903): Hiring a room to watch a coronation procession was frustrated when the procession was cancelled.
  • Herne Bay Steam Boat Co v Hutton (1903): A boat hired to see the naval review and cruise round the fleet was not frustrated when the review was cancelled, because the fleet was still there.
  • Davis Contractors Ltd v Fareham UDC (1956): A building contract was not frustrated just because labour shortages made it take much longer and cost much more.
  • Hochster v De la Tour (1853): A courier told in advance that he would not be needed could sue at once, without waiting for the start date.

Key terms

  • Discharge: When contractual obligations come to an end: by performance, agreement, frustration or breach.
  • Substantial performance: Where a party has essentially completed their obligations with only minor defects, they are entitled to the price, less the cost…
  • Frustration: When an event after the contract is made, which is neither party's fault, makes performance impossible, illegal or radically…
  • Anticipatory breach: When a party makes clear, before performance is due, that they will not perform. The other party can treat the contract as ended…
  • Repudiatory breach: A breach serious enough to let the innocent party end the contract, such as a breach of a condition or a serious breach of an…
  • Condition: An important term that goes to the root of the contract. If it is broken, the innocent party can end the contract and claim…
  • Warranty: A less important term. If it is broken, the innocent party can claim damages but cannot end the contract. (In everyday speech a…

Try a question

Discharge of a contract

What can the innocent party do after a repudiatory breach?

  1. End the contract and claim damages, or affirm it and claim damages
  2. Only claim damages
  3. Nothing, because the contract continues
  4. Only end the contract, with no damages
Show the answer

End the contract and claim damages, or affirm it and claim damages. A repudiatory breach gives the innocent party a choice: terminate or affirm, and damages either way.

22 questions on this topic in the app, plus written questions marked by AI.

This page is a summary. The full topic in Veritas has the law step by step, worked examples, exam tips and practice questions. Full A4 revision sheets with the nutshell are part of Veritas Premium.