Sumpter v Hedges
A builder who abandoned the work could not be paid for it, because the landowner had no real choice but to accept the half-built buildings.
- Citation
- [1898] 1 QB 673
- Court
- Court of Appeal
- Year
- 1898
- Topic
- Discharge of a contract
The facts
A builder agreed to build two houses and stables on Hedges' land for £565. He did work worth about £333, then ran out of money and abandoned the job. Hedges finished the buildings himself, using materials the builder had left on the site.
The issue
Could the builder recover for the work done and the materials left behind?
The decision
Only for the materials.
Why it matters
Explains when acceptance of partial performance creates a duty to pay.
Use it for
Use it when a party abandons work and the other side completes it.