Meaning
A method that maps how a project's tasks depend on each other and finds the critical path: the longest chain of dependent tasks. Any delay to a task on it delays the whole project.
Example
Installing new software is on the critical path, because training cannot start until it is done.
Where it comes from
Developed in the 1950s; uses network diagrams.