Project tools, teams and responsibilities: 10 questions
Print it for a lesson starter or homework. The answers are on a separate page.
Name: ______________________ Date: ____________
Training was budgeted at £5,000 but cost £6,500. What is this?
- An adverse variance of £1,500
- A favourable variance of £1,500
- A return on investment of 30%
- A critical path
A project's IT costs were budgeted at £8,000 but came to £7,200. What is this?
- A favourable variance of £800
- An adverse variance of £800
- A critical path
- A tender
What does "Gantt chart" mean?
- A bar chart showing a project's tasks against a timeline, so it is easy to see when each task happens, what overlaps and whether the project is on schedule.
- Information gathered first-hand for the research, through questionnaires, surveys, interviews, observation, focus groups and online communities.
- The three constraints on every project, scope, cost and time, with quality in the middle.
- A method that maps how a project's tasks depend on each other and finds the critical path: the longest chain of dependent tasks.
What does "Critical path analysis" mean?
- BAILII (British and Irish Legal Information Institute) gives free online access to many judgments and some legislation.
- A document justifying a project before it starts: the problem, the options, the advantages, timescales, costs, return on investment and risks.
- When people oppose or delay change, often because they fear for their jobs, dislike new ways of working or do not understand why it is needed.
- A method that maps how a project's tasks depend on each other and finds the critical path: the longest chain of dependent tasks.
What does "Project sponsor and project manager" mean?
- The project sponsor is a senior person who champions the project, provides funding and makes major decisions.
- An organisation that campaigns to influence government policy, businesses or public opinion on a particular issue.
- Writing that explains or comments on the law, such as textbooks, journal articles and practitioner guides.
- A published collection of important judgments.
What does "Variance analysis" mean?
- A document justifying a project before it starts: the problem, the options, the advantages, timescales, costs, return on investment and risks.
- Comparing actual results with the budget.
- A list at the end of a piece of work of all the sources used, written in a consistent referencing format.
- A one-sided view that favours a particular position, often because the author has an interest in it.
What does "Tendering" mean?
- When a trusted person or business recommends a client to a legal service, such as a satisfied client, an accountant or an estate agent.
- Legal work that involves a dispute, whether or not it reaches court, such as suing for money owed, an employment claim or a criminal defence.
- The government's own legal service, employing lawyers who advise government departments and represent them in court.
- A formal process in which organisations bid for a contract, usually by submitting a proposal and price that the buyer compares against others.
What does "Stakeholder" mean?
- Anyone with an interest in, or affected by, what a business does.
- An organisation, such as a charity, that raises money and may make a surplus, but puts that surplus back into its social, environmental or cultural aims rather than…
- A tax on the profits of limited companies.
- A merger is when two businesses combine into one.
A Gantt chart shows tasks over time; ____ finds the longest chain of dependent tasks.
- bAILII and legal databases
- critical path analysis
- project life cycle
- lewin's change model
Budgets are monitored by ____: favourable if better than planned, adverse if worse.
- bAILII and legal databases
- variance analysis
- bias
- plagiarism
Answers
- A: An adverse variance of £1,500. Spending more than budgeted is an adverse variance.
- A: A favourable variance of £800. Spending less than planned is better than budget, so it is a favourable variance.
- A: A bar chart showing a project's tasks against a timeline, so it is easy to see when each task happens, what overlaps and whether the project is on schedule.. Gantt chart: A bar chart showing a project's tasks against a timeline, so it is easy to see when each task happens, what overlaps and whether the project is on schedule.
- D: A method that maps how a project's tasks depend on each other and finds the critical path: the longest chain of dependent tasks.. Critical path analysis: A method that maps how a project's tasks depend on each other and finds the critical path: the longest chain of dependent tasks. Any delay to a task on it delays the whole project.
- A: The project sponsor is a senior person who champions the project, provides funding and makes major decisions.. Project sponsor and project manager: The project sponsor is a senior person who champions the project, provides funding and makes major decisions. The project manager plans and runs it day to day.
- B: Comparing actual results with the budget.. Variance analysis: Comparing actual results with the budget. A favourable variance is better than planned (such as costs lower than budgeted); an adverse variance is worse.
- D: A formal process in which organisations bid for a contract, usually by submitting a proposal and price that the buyer compares against others.. Tendering: A formal process in which organisations bid for a contract, usually by submitting a proposal and price that the buyer compares against others.
- A: Anyone with an interest in, or affected by, what a business does.. Stakeholder: Anyone with an interest in, or affected by, what a business does. Internal stakeholders are inside the business (owners, managers, employees); external stakeholders are outside it (customers, suppliers,…
- B: critical path analysis. A Gantt chart shows tasks over time; critical path analysis finds the longest chain of dependent tasks.
- B: variance analysis. Budgets are monitored by variance analysis: favourable if better than planned, adverse if worse.