  1. A £20,000 project brings £30,000 of benefits. What is its return on investment?

    1. 50%
    2. 150%
    3. 33%
    4. 10%
  2. A client asks for two extra features on a project but will not move the deadline. Under the project triangle, what is most likely to happen?

    1. The cost rises, or quality drops
    2. Nothing changes
    3. The project becomes cheaper
    4. The scope gets smaller
  3. What does "Business case" mean?

    1. A measurable value showing how well a business, team or project is meeting a key objective.
    2. A document justifying a project before it starts: the problem, the options, the advantages, timescales, costs, return on investment and risks.
    3. A bar chart showing a project's tasks against a timeline, so it is easy to see when each task happens, what overlaps and whether the project is on schedule.
    4. How much benefit a project or investment brings compared with its cost, often shown as a percentage: (gain − cost) ÷ cost × 100.
  4. What does "Return on investment" mean?

    1. A plan setting out a research project's aims, planned outcomes, task dates and milestones, review dates and how progress will be monitored.
    2. The stages of a project: initiation, planning, execution, closure and evaluation.
    3. How much benefit a project or investment brings compared with its cost, often shown as a percentage: (gain − cost) ÷ cost × 100.
    4. Writing that explains or comments on the law, such as textbooks, journal articles and practitioner guides.
  5. Which term means: "The three constraints on every project, scope, cost and time, with quality in the middle."

    1. Neutral citation
    2. Resistance to change
    3. Primary legal source
    4. Project management triangle
  6. What does "Project life cycle" mean?

    1. Information gathered first-hand for the research, through questionnaires, surveys, interviews, observation, focus groups and online communities.
    2. When people oppose or delay change, often because they fear for their jobs, dislike new ways of working or do not understand why it is needed.
    3. A method that maps how a project's tasks depend on each other and finds the critical path: the longest chain of dependent tasks.
    4. The stages of a project: initiation, planning, execution, closure and evaluation.
  7. What does "Key performance indicator" mean?

    1. A measurable value showing how well a business, team or project is meeting a key objective.
    2. A published collection of important judgments.
    3. BAILII (British and Irish Legal Information Institute) gives free online access to many judgments and some legislation.
    4. The moral principles that govern how researchers work: informed consent, protecting privacy and confidentiality, avoiding harm, honesty about methods and results, and…
  8. Which term means: "Objectives that are Specific, Measurable, Achievable, Realistic and Time-bound, so it is clear what success looks like and when it must be reached."

    1. Key performance indicator
    2. Neutral citation
    3. Project sponsor and project manager
    4. SMART objectives
  9. A ____ sets out the problem, options, advantages, timescales, costs, ROI and risks.

    1. primary research
    2. business case
    3. research plan
    4. law report
  10. A new document system costs £20,000 and is expected to produce gains of £26,000. What is the return on investment?

    1. 30%
    2. 130%
    3. 23%
    4. £6,000

Answers

  1. A: 50%. ROI = (gain − cost) ÷ cost × 100 = (£30,000 − £20,000) ÷ £20,000 × 100 = 50%.
  2. A: The cost rises, or quality drops. Scope, cost and time are linked: more scope in the same time needs more money, or quality suffers.
  3. B: A document justifying a project before it starts: the problem, the options, the advantages, timescales, costs, return on investment and risks.. Business case: A document justifying a project before it starts: the problem, the options, the advantages, timescales, costs, return on investment and risks.
  4. C: How much benefit a project or investment brings compared with its cost, often shown as a percentage: (gain − cost) ÷ cost × 100.. Return on investment: How much benefit a project or investment brings compared with its cost, often shown as a percentage: (gain − cost) ÷ cost × 100.
  5. D: Project management triangle. Project management triangle: The three constraints on every project, scope, cost and time, with quality in the middle. Changing one affects the others, or the quality.
  6. D: The stages of a project: initiation, planning, execution, closure and evaluation.. Project life cycle: The stages of a project: initiation, planning, execution, closure and evaluation.
  7. A: A measurable value showing how well a business, team or project is meeting a key objective.. Key performance indicator: A measurable value showing how well a business, team or project is meeting a key objective.
  8. D: SMART objectives. SMART objectives: Objectives that are Specific, Measurable, Achievable, Realistic and Time-bound, so it is clear what success looks like and when it must be reached.
  9. B: business case. A business case sets out the problem, options, advantages, timescales, costs, ROI and risks.
  10. A: 30%. ROI = (gain − cost) ÷ cost × 100 = (£26,000 − £20,000) ÷ £20,000 × 100 = 30%.